Millennium
Project Number: M-2002-004
Project
Title: Ground Probing Penetrating
Imaging Radar
Project Start Date: 2002
Projected End Date: NA
Technical Details:
Guided horizontal directional drilling equipment
is being increasingly used for the installation
of gas mains. This method can be less expensive
than traditional "open cut" installations but
has an associated risk of impacting existing
underground utilities. Loss of service and associated
repair costs can be significant. Even with the
use of traditional mark out services, damages
can occur.
The goal of this project is to develop a ground
penetrating radar system for horizontal directional
drilling systems to detect obstacles in the
drill path. The focus will be on development
of a drillhead-mounted system.
This project has successfully demonstrated the technology and work is now being continued through a separate OTD project.
View
Funding for Millennium Project M-2002-004